Upgrade Interconnection - FFM3-FFM5

Scheduled Maintenance Report for aurologic GmbH

Completed

The scheduled maintenance has been completed.
Posted Jun 06, 2025 - 10:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 05, 2025 - 10:00 UTC

Scheduled

We'll be implementing an upgrade of the interconnection between Digitalrealty and Equinix Frankfurt, increasing available capacity to 2x 1.6Tbps DWDM, enhancing the Frankfurt am Main Ring to 5.4 Tbps overall (FFM1/FFM3/FFM5).
Posted Mar 29, 2025 - 19:23 UTC
This scheduled maintenance affected: Network Infrastructure (Interconnection).