Upgrade Interconnection - HEL1-HEL2

Scheduled Maintenance Report for aurologic GmbH

Completed

The scheduled maintenance has been completed.
Posted May 29, 2026 - 11:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 29, 2026 - 10:00 UTC

Scheduled

We're adding additional wavelengths between HEL1 (Hetzner Helsinki) and HEL2 (Digita Helsinki) to increase capacity between both sites.
Posted May 12, 2026 - 09:05 UTC
This scheduled maintenance affected: Network Infrastructure (Interconnection).