Hardware Upgrade - core01/core02.hel1.fi

Scheduled Maintenance Report for aurologic GmbH

Completed

The scheduled maintenance has been completed.
Posted Jun 26, 2026 - 11:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 26, 2026 - 10:00 UTC

Scheduled

We're upgrading our core routers at HEL1 (Hetzner Helsinki) onto two Arista 7500R platform devices, also replacing Juniper egress/peering routers as well as to increase port density due to growing traffic demands.

Customers will be informed seperately and we plan migrating their ports throughout Q3/2026.
Posted May 12, 2026 - 09:09 UTC
This scheduled maintenance affected: Datacenter Infrastructure (HEL1 - Hetzner Helsinki).