UPS Maintenance - RR.A.UV03-UPS

Scheduled Maintenance Report for aurologic GmbH

Completed

The scheduled maintenance has been completed.
Posted Jul 15, 2026 - 08:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 13, 2026 - 08:00 UTC

Scheduled

The authorized UPS maintenance service partner will carry out works on UPS device for RR.A UV03. During the maintenance works, we will carry out switching operations on the maintenance bypass of the related device to transfer the electrical loads. Since bypass switching operations are break-free, we do not expect any power interruption to power feeds connected on UV03, primarily relating to cabinet rows R05/R06 within RR.A.

Further details can be found on https://tornadodc.statuspage.io/incidents/rzgy2lqbg4ft
Posted Jun 18, 2026 - 21:53 UTC
This scheduled maintenance affected: Datacenter Infrastructure (FRA1 - Tornado Datacenter FRA1).